In Progress
Lesson 1, Topic 1
In Progress

2EM 1.2 Conceptual Bridging: Problem Involving Inverse Proportion

A building can be completed in \(120\) days with \(50\) workers. Assuming that all the workers work at the same rate. Find the number of days it takes to complete the building with \(20\) workers.

Please login for access to this video. Login

Responses