A contractor was awarded a tender to construct \(4\) houses within \(180\) days. He hired \(24\) men for the job. After \(60\) days, he found that they had completed only \(1\) house. Each hired man works at the same constant rate. How many more men should he employ to complete the job within \(180\) days?

Video Solution:

Video Solution

Video solution locked

A free account saves your progress; this video needs a course plan.

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:\(12\) more men