Six workers can complete a project in \(d\) days. If one worker is absent, the remaining five take 4 more days.

  1. Find \(d\).
  2. To finish the project in 8 days, how many more workers than the original six are needed? State an assumption.

Solution:

Solution locked

Sign in to view the step-by-step solution

Similar questions are unavailable for this question.
Answer:(a) \(20\) days; (b) \(9\) more workers; equal constant work rates.