Hiring workers for an earlier finish

Hiring workers for an earlier finish

Secondary 2
TGM Original Questions

A mural takes \(36\) workers \(50\) days. How many more workers are needed to finish \(10\) days earlier, assuming equal work rates?

Solution:

Solution locked

Hundreds of questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:\(9\) more workers.