Hoses and workforce deadlines

Hoses and workforce deadlines

Secondary 2
TGM Original Questions
  1. Six identical hoses water a garden in \(30\) minutes. How many minutes will eight hoses take, to the nearest minute?
  2. A job takes \(24\) days with \(48\) workers. To finish \(6\) days earlier, how many more workers are needed?

Solution:

Solution locked

Sign in to view the step-by-step solution

Similar questions are unavailable for this question.
Answer:(a) \(23\) min; (b) \(16\) more workers.