Inverse relation and paving rate
Secondary 2
TGM Original Questions
The quantity \(a\) varies inversely as \(b+3\). The sum of its values when \(b=-2\) and \(b=3\) is \(70\). Find \(a\) when \(b=-5\).
Six workers pave \(240\) m of road in \(5\) hours. How long will ten workers take to pave \(600\) m?
Solution:
Solution locked
Sign in to view the step-by-step solution
Sign in to view
E Math Tuition
Similar Questions
Similar questions are unavailable for this question.
Answer:
(a) \(a=-30\); (b) \(7.5\) h.