Extra workers for an earlier deadline

Extra workers for an earlier deadline

Secondary 2
TGM Original Questions

Eight workers can complete a job in \(35\) days. How many extra workers are needed to complete it in \(20\) days, assuming equal rates?

Solution:

Solution locked

Sign in to view the step-by-step solution

Similar questions are unavailable for this question.
Answer:\(6\) extra workers.