Working hours after workers leave

Secondary 2
3 marks
TGM Original Questions

Core stretch

Assume equal constant individual rates and no efficiency change.

Fifteen workers, working \(8\) hours per day, plan to finish a project in \(6\) days. After two days, five workers leave. How many hours per day must the remaining workers work for the last four days?[3]

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:\(12\) h per day.