Labour Cost and Work Rate Problem

Labour Cost and Work Rate Problem

Secondary 2

A construction firm pays its worker \(\$100\) each per day and each worker works at the same rate. If \(15\) workers are able to complete a project in \(30\) days,

  1. calculate the total labour cost of the project,
  2. find how many workers needed to be hired if the project must be completed in \(10\) days,
  3. determine whether the total labour cost will be affected as a result of hiring more workers in part (b). Show your working clearly.

Video Solution:

Video Solution

Video solution locked

A free account saves your progress; this video needs tuition enrolment.

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs tuition enrolment.

Create a free account to practise similar questions.

Answer:(a) \(\$45\,000\). (b) \(45\) workers in total. (c) No change: \(\$45\,000\).