It takes \(4\) workers to paint a house in \(1\frac{1}{2}\) days. Assuming the workers paint at the same rate,

  1. how many days will \(3\) workers take to paint the same house?
  2. how many more workers are needed if the house is to be painted in half a day?
  3. how many days will \(6\) workers take to paint \(5\) such houses?

Video Solution:

Video Solution

Video solution locked

A free account saves your progress; this video needs a course plan.

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:(a) \(2\) days (b) \(8\) more workers (c) \(5\) days