Work rates

Work rates

Secondary 2
4 marks
TGM Original Questions

Six workers can complete a project in \(d\) days. If one worker is absent, the remaining five take 4 more days. Assume that every worker works at the same constant rate and that adding workers does not reduce efficiency.

  1. Find \(d\).[2]
  2. To finish the project in 8 days, how many more workers than the original six are needed? State an assumption used in your calculation.[2]

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:(a) \(20\) days; (b) \(9\) more workers; equal constant work rates.