Eight workers can complete a job in \(15\) days. After working together for \(5\) days, three workers leave.
Assume equal constant work rates and no interruption.
What fraction of the job has been completed after \(5\) days?
How many additional days will the remaining workers need?
How many days late will the job finish compared with the original schedule?