Reduced construction workforce

Reduced construction workforce

Secondary 2
3 marks
TGM Original Questions

Assume constant individual rates, no interruptions and no change in efficiency when the number of workers or machines changes. For consumption, assume equal constant consumption per person.

A construction task requires \(60\) workers for \(9\) hours. Fifteen workers are absent. How long must the remaining workers work to complete the same task?[3]

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:\(12\) hours.