Secondary 2

Five workers complete a job in \(12\) days. Each worker earns \(\$80\) per day. Workers have equal constant work rates, and only wages are considered.

  1. How many days would eight workers take?

  2. Compare the total wage bills for the two teams. Assume payment is proportional to time worked, including part-days.

Solution:

Solution locked

Hundreds of questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:(a) \(7.5\) days; (b) Both cost \(\$4{,}800\).