Direct and Inverse Proportion - Combined Proportion

Direct and Inverse Proportion - Combined Proportion

IP 2

Eighteen workers are scheduled to complete a project in \(20\) days. After working for \(5\) days, \(6\) workers leave.

  1. Find how many additional days the remaining workers need.

  2. Find the delay relative to the original schedule.

  3. Instead, suppose replacement workers can join immediately after day \(5\). What is the minimum number of additional workers needed then to finish by the end of day \(18\)?

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs tuition enrolment.

Create a free account to practise similar questions.

Answer:(a) \(22.5\) additional days; (b) \(7.5\) days late; (c) \(9\) additional workers.

Need help? Join our IP Math tuition programme.

Learn more