Six workers can complete a job in \(10\) days, working \(8\) hours a day. All workers have the same constant hourly rate. Four workers start the job and work \(6\) hours a day for \(5\) days. Find the remaining work in worker-hours.
[3]The job must finish in \(4\) more days, with everyone working \(9\) hours per day. Find the minimum number of additional workers who must join immediately.