Fifteen workers, working \(8\) hours per day, plan to finish a project in \(6\) days. After two days, five workers leave. How many hours per day must the remaining workers work for the last four days?[3]

Solution:

Solution locked

Sign in to view the step-by-step solution

Please join our E Math programme to search for similar questions for more practice.

E Math Tuition
Answer:\(12\) h per day.