  1. 6 workers can paint a building in 44 days. Find the additional number of workers needed if the building is to be painted in 11 days.[3]
  2. \(A\) is inversely proportional to \(B^2\). If \(B\) increases by 20%, find the percentage decrease in \(A\).[2]

Solution:

Solution locked

Sign in to view the step-by-step solution

Similar questions are unavailable for this question.
Answer:(a) \(18\) (b) \(30.6\%\)