2025 MSHS PRELIMS P1 Q11

2025 MSHS PRELIMS P1 Q11

Secondary 4
5 marks
  1. 6 workers can paint a building in 44 days. Find the additional number of workers needed if the building is to be painted in 11 days.[3]
  2. \(A\) is inversely proportional to \(B^2\). If \(B\) increases by 20%, find the percentage decrease in \(A\).[2]

Solution:

Solution locked

680+ questions here come with free worked solutions. A free account saves your questions and progress; this one needs a course plan.

Answer:(a) \(18\) (b) \(30.6\%\)

Need help? Join our E-Maths tuition for the SEC, the exam that replaces the O-Levels.

Learn more